American Dryer Corp. MLG-460 Clothes Dryer User Manual


 
9
2. Reassembly Instructions For Dryers Shipped In Three (3) Pieces
When the dryer is shipped in three pieces, the tumbler and the tumbler base sections are shipped as two (2)
separate pieces. The heat console section is shipped as the third piece.
a. Reassemble The Tumbler (Basket) Base Section To The Heat Console Section
Move the heat console section into position by using cables through the eye bolts located at the top of the
section or by using a fork truck and lifting the section from underneath. The tumbler (basket) base section
is now moved into position with a fork (lift) truck. The seven (7) clearance holes located on the right side
of the tumbler (basket) base section (four [4] holes in front and three [3] at the back of the section) must
be aligned with the seven (7) 3/8-16 tapped holes on the left side of the heat console section. Use the
3/8-16 x 3” long bolts and the tapered shims supplied with the unit to bolt the section together.
b. Reassemble The Tumbler (Basket) Section Over The Tumbler (Basket) Base
Slowly lower the tumbler (basket) section over the tumbler base. The four (4) large slots located on the
bottom of the tumbler (basket) section (one slot at each corner of the tumbler [basket] section) must be
aligned with the top of the pistons in the tumbler base section. Use the four (4) 1-1/4-12 x 3-1/2” long bolts
supplied with the unit to secure the tumbler (basket) section to the tumbler (basket) base section.
c. Reattach The Control Pendant Arm
Position the control pendant arm to the top front of the heat console section by aligning the clearance
holes in the arm with the 1/4-20 tapped holes on the top of the heat console section. Use the 1/4-20 x 3”
long bolts supplied with the machine to attach the arm to the console.
d. Reconnect The Internal Air, Electric Connections, and Water Connections (refer to page 12 through
page 19).
3. Reassembly Instructions for Dryer Shipped in Four Pieces
In this method of shipment the tumbler section, tumbler (basket) base, lower heat console, and upper heat
console are ALL shipped as separate sections.
a. Reassemble The Heat Console Section
Apply silicone (provided with unit) to the flanges of the lower heat console section. Lift the upper heat
console section by use of cables through the eyebolts located on the top of the upper console section.
Position the upper heat console over the lower heat console section. Use the 5/16-18 hardware provided
with the machine to secure the sections together.
b. Reassemble The Tumbler (basket) Base Section To The Heat Console Section
Move the heat console section into position by using cables through the eyebolts located at the top of the
section or by using a fork (lift) truck and lifting the section from underneath. The tumbler (basket) base
section is now moved into position with a fork (lift) truck. The seven (7) clearance holes located on the
right side of the tumbler (basket) base section (four [4] holes in the front and the three [3] at the back of
the section) must be aligned with the seven 3/8-16 tapped holes on the left side of the heat console
section. Use the 3/8-16 x 2” long bolts and the tapered shims supplied with the unit to bolt the sections
together.