Conair 100 Clothes Dryer User Manual


 
G-8 l Appendix
Preparing for Installation
The MDC has been designed for use beside the processing machine. The mobile
unit also can be used for pre-drying in a remote location.
1 Make sure the location for the MDC provides:
A grounded power source supplying the correct current for your dryer
model. Check the dryer’s serial tag for the correct amps, voltage, phase and
cycles. Field wiring should be completed by qualified personnel to the planned
location for the dryer. All electrical wiring should comply with your region’s
electrical codes.
A source of water, if you have an aftercooler. The dryer’s optional aftercooler
can use tower or city water at temperatures of 40° to 85°F (4° to 29°C). Pipe
should be run to the planned dryer location. Use flexible hose to connect the
water pipes to the aftercooler.
Minimum clearance for safe operation and maintenance. The MDC should
not be placed near flammable or combustible materials during operation. We
recommend at least 25 inches (63.5 cm) clearance above the dryer for removing
the carousel housing. You will need at least 24 inches (61 cm) clearance on any
side of the MDC for access to components that need cleaning or servicing.
2 Mount the vacuum receiver mounting bracket. Lay out the bolt pattern of
the processing machine feed throat on the blank base plate of the vacuum
receiver mounting bracket and gasket. Drill holes for the mounting bolts you
plan to use. Place the gasket between the feed throat and mounting bracket.
Bolt the mounting bracket to the feed throat.
NOTE: You will receive a
4”x4” or 6”x6” mounting
bracket, as specified in your
order. If you need a larger
mounting bracket, call your
Conair sales representative.
Mounting bracket
Gasket
Drill mounting
bolt holes
6 in.
4 in.
6 in.
4 in.
Central
When configured as
a central dryer, the
MDC option is not
available.