Installation
37
F232135
© Copyright, Alliance Laundry Systems LLC – DO NOT COPY or TRANSMIT
Concrete Foundation Installation
A concrete foundation pad may be constructed to
elevate the machines. Refer to Figure 25, Figure 26 or
Figure 27 for a typical concrete foundation
installation.
NOTE: Expansion bolts should not be used in
single-machine concrete foundation installations.
1. Verify that the floor meets the requirements given
in the Machine Foundation section.
2. Excavate the floor to a depth of approximately
9 inches (230 mm) below the floor surface,
making certain that the sides of the hole slope
outwards from top to bottom. The bottom of the
hole should be 6 inches (152 mm) larger all
around than the top.
NOTE: When installation is complete, the top
of the foundation should extend a minimum of
4 inches (102 mm) out from the machine on all
sides.
3. Wet the hole well and brush the bottom and sides
with cement grout.
Figure 25
CHM2033N
1 Pad height must not exceed 8 in. (203 mm)
2 1 in. (25 mm) Minimum
3 4 in. (102 mm) Minimum
CHM2033N
2
3
18, 20, 25, 27, 30, 35, 40, 50 AND 60 POUND CAPACITY MODELS
1
3