American Dryer Corp. EURO-35 Clothes Dryer User Manual


 
12
E. EXHAUST REQUIREMENTS
Exhaust duct work should be designed and installed by a qualified professional. Improperly sized duct work will
create excessive back pressure which results in slow drying, increased use of energy, and shutdown of the burner
by the airflow (sail) switch, burner hi-limit, or lint chamber hi-heat protector thermostat.
Wherever possible, it is suggested that a separate (single) exhaust duct be provided for each dryer.
CAUTION: IMPROPERLY SIZED OR INSTALLED EXHAUST DUCT WORK CAN
CREATE A POTENTIAL FIRE HAZARD.
CAUTION: DRYER MUST BE EXHAUSTED TO THE OUTDOORS.
The exhaust duct work should be laid out in such a way that the duct work travels as directly as possible to the
outdoors with as few turns as possible. The shape of the duct work is not critical so long as the minimum cross
section area is provided. Single or independent dryer venting is recommended.
It is suggested that the use of 90° turns be avoided; use 30° or 45° angles instead.
The duct work should be smooth inside with no projections from sheet metal screws or other obstructions which
will collect lint. When adding ducts, the ducts to be added should overlap the duct to which it is connected. ALL
duct work joints must be taped to prevent moisture and lint from escaping into the building. Additionally,
inspection doors should be installed at strategic points in the exhaust duct work for periodic inspection and
cleaning.
IMPORTANT: When connecting duct work to the dryer exhaust duct, be sure that when screws are
used they DO NOT restrict the operation (both opening and closing) of the damper.
NOTE: When the exhaust duct passes through a wall, ceiling, or roof made of combustible materials,
the opening must be 2-inches (5 cm) larger (all the way around) than the duct. The duct must
be centered within this opening.
To protect the outside end of horizontal duct work from the weather, a 90° elbow bent downward should be
installed where the exhaust exits the building. If the duct work travels vertically up through the roof, it should be
protected from the weather by using a 180° turn to point the opening downward. In either case, allow at least
twice the diameter of the duct between the duct opening and the nearest obstruction (i.e., roof or ground level).
IMPORTANT: DO NOT use screens or caps on the outside of opening of exhaust duct work.
IMPORTANT: Exhaust back pressure measured by a manometer at the dryer exhaust duct area must
not exceed 0.3 inches of water column (0.75 mbar).