American Dryer Corp. ADG / MLG-170DR Clothes Dryer User Manual


 
113409-2 www.amdry.com 17
The ductwork should be smooth inside with no projections from sheet metal screws or other obstructions, which
will collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected.
ALL ductwork joints must be taped to prevent moisture and lint from escaping into the building. Inspection doors
should be installed at strategic points in the exhaust ductwork for periodic inspection and cleaning of lint from the
ductwork.
NOTE: When the exhaust ductwork passes through a wall, ceiling, or roof made of combustible materials, the
opening must be 2-inches (5.08 cm) larger than the duct (all the way around). The duct must be
centered within this duct.
Outside Ductwork Protection
To protect the outside end of the horizontal ductwork from the weather, a 90° elbow bent downward should be
installed where the exhaust exits the building. If the exhaust ductwork travels vertically up through the roof, it
should be protected from the weather by using a 180° turn to point the opening downward. In either case, allow
at least twice the diameter of the duct between the duct opening and the nearest obstruction.
IMPORTANT: DO NOT use screens, louvers, or caps on the outside opening of the exhaust ductwork.