Installation and connection
61
Installation
Levelling the dryer
Make sure the dryer door can be
opened without hindrance after in‐
stallation.
The appliance must stand perfectly lev‐
el to ensure safe and proper operation.
The screw feet can be adjusted to com‐
pensate for any unevenness in the floor.
Ventilation
The cool air intake at the front of
the dryer must not be blocked or
covered. This would hinder a suffi‐
cient intake of cool air for the heat
exchanger.
Do not block the gap between
the bottom of the tumble dryer and
the floor with plinth facings, deep
pile carpet etc. This would hinder a
sufficient flow of air to the dryer.
Air which is taken in to cool the heat
exchanger is then blown back out of
the dryer and warms up the air in the
room. It is therefore very important to
ensure adequate ventilation, e.g. by
opening a window. Otherwise drying
durations may be longer (increased en‐
ergy requirement).
Before moving the tumble dryer
again (e.g. when moving house)
After each use a small quantity of con‐
densed water will collect in the area of
the pump. This water can run out if the
tumble dryer is tipped up when it is be‐
ing moved. Recommendation: run the
Warm air programme for approximately
1 minute before moving the tumble dry‐
er. Any remaining condensed water will
then be fed into the condensed water
container or out through the drain hose.