American Dryer Corp. AD-115ES Clothes Dryer User Manual


 
14
C. DRYER ENCLOSURE REQUIREMENTS
It is recommended that the rear of the dryer be positioned approximately 3 feet (0.91 meters) from the nearest
obstruction (i.e., wall) for ease of installation, maintenance, and service. Bulkheads and partitions should be
made of noncombustible materials. The bulkhead facing must not be closed in
ALL the way to the top of the
dryer. A 2-inch (5.08 cm) clearance is required.
NOTE: Bulkhead facing should not be installed until after dryer is in place. Ceiling area must be
located a minimum of 12-inches (30.48 cm) above the top of the dryer.
IMPORTANT: Even though a minimum of only 12-inches (30.48 cm) is required, 18-inches (45.72 cm)
or more is
suggested for steam dryers and especially in cases where sprinkler heads
are over the dryers.
NOTE: When fire sprinkler systems are located above the dryers, a minimum of 18-inches (45.72 cm)
above the dryer console (module) is suggested. Dryers may be positioned side wall to side
wall however, 1 or 2 inches (2.54 or 5.08 cm) is suggested between dryers (or wall) for ease
of installation and maintenance. Allowances must be made for the opening and closing of the
control and lint doors.