B. ADJUSTMENTS
7 DAYS AFTER INSTALLATION AND EVERY 6 MONTHS THEREAFTER
Inspect bolts, nuts, screws, setscrews, grounding connections, and nonpermanent gas connections (unions, shutoff valves,
and orifices). Motor and drive belts should be examined. Cracked or seriously frayed belts should be replaced.
Tighten loose V-belts when necessary. Complete operational check of controls and valves. Complete operational check
of ALL safety devices (door switch, lint drawer switch, sail switch, burner, and hi-limit thermostats).
30 DAYS AFTER INSTALLATION
SHUT OFF ALL POWER TO THE DRYER. Verify that the electrical connections to the motor contactors and
overloads are tight. This is done to accommodate the compression of the wires over time.
YEARLY
WARNING: Twisting of the gas line may cause premature failure.
Inspect flex gas lines for leaks; if any signs of fraying or abrasion are found, the gas line must be replaced.
C. LUBRICATION
MONTHLY
The two (2) bearings that support the impellor/fan shaft must be lubricated. Use Shell Alvania #2 grease or its equivalent.
Generically, this grease would be described as an NLGI Grade 2 multipurpose industrial grease with a lithium thickener
and mineral base oil.
EVERY 3 MONTHS
The four (4) bearings that support the drive and idler shafts must be lubricated. Use Shell Alvania #2 grease or its
equivalent. Generically, this grease would be described as an NLGI Grade 2 multipurpose industrial grease with a
lithium thickener and mineral base oil.