A SERVICE OF

logo

ELECTRIC FRYERS - REMOVAL AND REPLACEMENT OF PARTS
7
8. Remove the screws from the rear top of the
head cover.
9. Lift cover enough to access element wires.
Identify the six lead wire connections for
connection later. Then disconnect the six lead
wires from the element being removed.
NOTE:
Each heater has three elements inside and
two wire connections for each element.
10. Remove the element.
11. Reverse procedure to install.
PROBE
WARNING:
DISCONNECT THE ELECTRICAL
POWER TO THE MACHINE AT THE MAIN
CIRCUIT BOX. THERE MAY BE TWO SEPARATE
CIRCUITS. BE SURE BOTH ARE
DISCONNECTED. PLACE A TAG ON THE
CIRCUIT BOX INDICATING THE CIRCUIT IS
BEING SERVICED.
NOTE:
Dont bend or kink high limit capillary tube.
1. Raise the heating elements and allow to drain.
2. Remove screws securing the bottom of the
head cover.
3. Remove the clamps from the probe.
4. Lower the element enough to remove the
screws securing the top of the head cover.
5. Lift the head cover enough to access and
disconnect the probe lead wires.
6. Reverse procedure to install.
7. Check temperature control for calibration as
outline under "TEMPERATURE CONTROL
CALIBRATION".
HIGH LIMIT THERMOSTAT
WARNING:
DISCONNECT THE ELECTRICAL
POWER TO THE MACHINE AT THE MAIN
CIRCUIT BOX. THERE MAY BE TWO SEPARATE
CIRCUITS. BE SURE BOTH ARE
DISCONNECTED. PLACE A TAG ON THE
CIRCUIT BOX INDICATING THE CIRCUIT IS
BEING SERVICED.
1. Raise the heating elements out of the
shortening and allow to drain.
2. Loosen the clamps around the bulb and
capillary tube.
3. Remove screws securing the bottom of the
head cover.
4. Lower the element enough to remove the
screws securing the top of the head cover.
5. Lift the head cover enough to access and
disconnect the lead wires.