Strata CTX670 Installation
Install Reserve Power
Strata CTX I&M 06/04 4-31
Strata CTX670
Installation
Reserve Power for Three or More Cabinets (Wall Mount)
1. Install the Battery Distribution Box (BBDB) to the bottom cabinet (see Figures 4-12 and 4-24).
The BCCB is not required for wall mount systems.
2. Connect two Cable ā€œCā€ jumper wires from the positive terminal of one 12VDC battery to the
negative terminal of the second 12VDC batter, per Figure 4-18 (Cable ā€œCā€ is supplied with the
BBTC1A-2.0M cable).
3. Ensure that a serviceable 15-amp fuse is installed in the in-line fuse holder of the BBTC1A-
2.0M battery cable.
4. Connect the white lead of the BBTC1A-2.0M battery cable to the open positive terminal of the
12VDC battery. Connect the black lead to the open negative terminal of the second 12VDC
battery.
5. Connect a second BBTC1A-2.0M in parallel to the first BBTC1A-2.0M cable per Steps 2, 3
and 4 instructions.
6. Plug the two BBTC1A-2.0M battery cables into the Battery Distribution Box.
Important! The cabinets must be connected to the (live) AC power source, and the power supply
On/Off switches set to On prior to the final step of connecting the reserve power
batteries to the power supplies via the BATT +/- receptacle. If the batteries are
connected after AC power is lost, reserve power will not function.
7. Connect the BBTC2A-2.0M cables from the Battery Distribution Box to the BATT +/-
receptacle of individual power supplies per Figure 4-12 (BBTC2A-2.0M cables are supplied
with an BBDB distribution box).
8. To test reserve power operation, disconnect the system AC power plugs with the power supply
On/Off switches in the On position. The system should continue to operate without
interruption.
Note If connecting four batteries, follow the wiring diagrams in Figure 4-18.