The illustration below shows the duct work connection points and what internal duct work is included in the
dryer.
The exhaust connection at the TOP basket (tumbler) must be made at the blower duct inside the cabinet. No
internal duct work is included for the TOP basket/tumbler. (Not available from ADC and must be
purchased elsewhere). Depending on the external duct work layout, the installer has the option of the duct
work coming out of the top of the back of the dryer. The duck work used inside of the dryer, from the blower
duct to where it exits the dryer, must be a minimum of 6-inches in diameter (30 square inches cross-sectional
area). At this point (where the internal ducting ends) the diameter must be increased to meet the application
as described further in this manual.
IMPORTANT: When connecting duct work to the top basket (tumbler) exhaust duct, be sure that
when screws are used they do not restrict the operation (both opening and closing)
of the damper.
IMPORTANT: ALL duct work joints must be taped to prevent moisture and lint from escaping
into the dryer and/or building.
The BOTTOM basket (tumbler) includes 6-inch duct work which extends from the dryer blower duct to the
lower back guard area. At this point the diameter must be increased to meet the application as described
further in this manual.