Connecting the RTD Probe
See “Connecting the RTD Probe” page 3-16
Connecting the Demand Sensor
The capacitive demand sensor monitors the level of material in the viewing cham-
ber of the vacuum receiver when the MDC is conveying. The sensor signals the
MDC control to start the conveying blower whenever the level of material drops
below the amount that you want to maintain at the feed throat.
1 Plug the sensor cable into the multi-pin connector on the side of the MDC
electrical enclosure.
Connecting the Main Power
See “Connecting the Main Power” page 3-10
Connecting the Water Hoses
See “Connecting Water Hoses” page 3-15
✒
TIP: Prevent damage to the
demand sensor cable by
attaching it to the return air
conveying line with a wire tie.
Do not tie the cable to the
smaller-diameter material
conveying line. Material
passing through the line will
generate static electricity and
noise in nearby electrical
cables.
Central
When configured as
a central dryer, the
MDC option is not
available.