American Dryer Corp. ADG-220 Clothes Dryer User Manual


 
5
SECTION III
INSTALLATION PROCEDURES
Installation should be performed by competent technicians in accordance with local and state codes. In the
absence of these codes, the installation must conform to applicable American National Standards: ANSI Z223.1-
LATEST EDITION (National Fuel Gas Code) or ANSI/NFPA NO. 70-LATEST EDITION (National Electrical
Code) or in Canada, the installation must conform to applicable Canadian Standards: CAN/CGA-B149.1-M91
(Natural Gas) or CAN/CGA-B149.2-M91 (Liquid Propane [L.P.] Gas) or LATEST EDITION (for General
Installation and Gas Plumbing) or Canadian Electrical Codes Parts 1 & 2 CSA C22.1-1990 or LATEST EDITION
(for Electrical Connections).
A. UNPACKING/SET UP
Remove shipping carton, polyethylene cover, and protective shipping corners from dryer.
NOTE: The access keys to the coin box, control (upper service) door, and lint (lower service)
door are shipped in the upper basket (tumbler) and should be removed and put in a safe
place.
The dryer can be moved to its final location while still attached to the skid or with the skid removed. To un-skid
the dryer, locate and remove the four (4) bolts securing the base of the dryer to the wooden skid. Two (2) are
located at the rear of the base, and two (2) are located in front. Once the bolts are removed, slide the dryer off the
skid.
With the skid removed, to make it easier to slide the dryer into its final position, slightly lower ALL four (4)
leveling legs, so that the dryer will slide on the legs instead of the base frame. The dryer is equipped with four (4)
leveling legs, one (1) at each corner of the dryer base.
B. LOCATION OF THE DRYER
Before installing the dryer, be sure the location conforms to local codes and ordinances. In the absence of such
codes or ordinances the location must conform with the National Fuel Gas Code ANSI.Z223.1 LATEST EDITION,
or in Canada, the installation must conform to applicable Canadian Standards: CAN/CGA-B149.1-M91 (Natural
Gas) or CAN/CGA-B149.2-M91 (L.P. Gas) or LATEST EDITION (for General Installation and Gas Plumbing).
1. The dryer must be installed on a sound level floor capable of supporting its weight. Carpeting must be
removed from the floor area that the dryer is to rest on.
IMPORTANT: “The dryer must be installed on noncombustible floors only.”
It is recommended that the rear of the dryer be positioned about 2 feet (0.61 meters) away from the nearest
obstruction (i.e., wall) for ease of installation, maintenance, and service.
2. The dryer must be installed with a proper exhaust duct connection to the outside.